Production Improvement for Manufacturing Furniture Company
(Polytechnic University of Puerto Rico, 2020)
This project was based on the
laminating production improvement for a
manufacturing furniture company. Basically, the
process consists of the laminated production of wood
materials. The lead time and ship dates of ...
Material Qualification Process Improvement to Reduce the Cycle Time
(Polytechnic University of Puerto Rico, 2019)
This project was focused in improving
the material qualification process, reducing the
cycle time. A Documentation Checklist and Tracking
Sheet System were created as part of the
improvements. The Documentation Checklist ...
Setup Time Reduction in the Water for Injection Sampling Process on the Pharmaceutical Industry
(Polytechnic University of Puerto Rico, 2020)
This work consists in the development of
a new WFI sampling route that will bring several
important benefits to the pharmaceutical industry.
Reduction in the setup time will improve daily
operations in terms of efficiency, ...
Estructura para Reconciliación de Lotes en Área de Encapsulación Utilizando la Metodología Esbelta (“Lean”)
(Polytechnic University of Puerto Rico, 2021)
La industria farmacéutica ha enfrentado muchos cambios con el paso del tiempo. La necesidad de adaptarse a estos cambios ha provocado que las farmacéuticas hayan tenido que adoptar diferentes metodologías para mantener la ...
Evaluation to Sleeves Used in Granulation Department for the Graduate Programs at Polytechnic University of Puerto Rico
(Polytechnic University of Puerto Rico, 2021)
The DMAIC methodology was applied to analyze a manufacturing system at Johnson & Johnson Pharmaceuticalsin Las Piedras, Puerto Rico. The methodology was used to improve the time for changing and ...
Optimization of the Registration Process of Products on the Pharmaceutical Industry of Puerto Rico
(Polytechnic University of Puerto Rico, 2018)
Registration Process for
pharmaceutical products in Puerto Rico has unique
requirements for the marketing, sale, and
distribution of the products. The Organizations
must be approved before they can market, sell ...
Suppliers Information Exchange Process Optimization
(Polytechnic University of Puerto Rico, 2018)
The emphasis of this research project
is to reduce the processing time for supplier’s
requests for change and/or information (RC/I), a
tool utilized to request information and/or change
in response to technical or ...
Application of Lean Manufacturing and Lean Six Sigma Tools to Improve Back to Back Activities in the Compression Process
(Polytechnic University of Puerto Rico, 2019)
A recent opportunity regarding a
product ramp up in the production schedule due to
a potential product transfer requires the
manufacturing area to look for creative ways to
improve in order to comply with expected ...
Reducción del Tiempo de Cambio para la Línea de Empaque#5
(Polytechnic University of Puerto Rico, 2018)
Se utiliza la técnica de Lean
Manufacturing con la metodología DMAIC para
reducir el tiempo de cambio o Changeover de la
línea de empaque#5. Para llevar a cabo su
implementación se midieron las fases de
culminación ...
Process Time Reduction in Manufacturing Areas: Visual Valves Identification on Manufacturing Area specifically on Media Prep Area, Media Preparation tanks to Pursue Agility on the Visual inspections required before, during and after the Media Prep Solution are Prepared
(Polytechnic University of Puerto Rico, 2022)
Time of production process and associate activities were evaluated for Media Prep manufacturing process on Juncos, P.R. The voice of the customer requested reduced time inspection process before, ...