The X Filed and Building Construction Site Approval
Resumen
The Facility Division is currently having an engineering problem considering a site approval for construction. The engineering
department need to analyze two locations and determine which one is better for the construction of The X Field and Building, taking into consideration the budget constraint of $2 Million. The methodology used during the site approval process was a feasibility analysis to compare the topography and utilities connections of the location, cost analysis to estimate the labor and
material cost of constructing in each site respectively, pros and cons analysis, and a weighted decision matrix. After analyzing the data and following the stablished methodology the engineering department determined that site #2 is the best location for the site approval for construction. Now, the design phase of the project can begin. Key Terms ⎯ decision process, feasibility analysis, construction planning, cost analysis, pros and cons analysis, site approvals, weighted decision matrix.