Cycle Time Reduction of a Crystallization Process in a Chemical Plant
Abstract
Estimates indicate that Diabetes will
increase affecting the population worldwide in the
future. To mitigate current and future demand,
Barceloneta’s Factory 2 needs to improve the
active pharmaceutical ingredient (API) for
Diabetes Type II manufacturing process. Several
stages in the manufacturing process have been
identified for improvement. This project focuses in
the Cycle Time Reduction of a Crystallization
Process. Six Sigma tools and methodologies
(Define, Measure, Analyze, Improve and Control)
were utilized to identify the problem and improve
the process. As a result we were able to optimize
the crystallization process, reducing the cycle time
to ≤ 20 hrs of the vessel and helping the train
ability to increase its manufacturing capacity with
an output 6.0 lots per week in 5 days / 3 shift.
Key Terms - Cycle Time, DMAIC,
Prioritization Matrix, Process Baseline.