New Material and Personal Lifting for Material Management Building
Resumen
A new elevator will be installed in the materials handling building of Lilly del Caribe. For it, a facility commissioning will be carried out, since where the stairs of the building are, it will be installed there. It will validate a protocol that has to comply with the regulations and specifications established by the industry and has 14 activities that must be completed. The existing elevator is only for material handling and can only exert a force capacity of 4,000 pounds. With the installation of the new freight elevator, the material can be handled and disposed of by the operator. Therefore, this elevator will improve the utilization and efficiency of such material handling. The new elevator can exert a force capacity of 10,000 pounds and being a new piece of equipment, it meets a 95% reliability. To execute the validation, DMAIC was used. Key Terms⎯ DMAIC, facility commissioning, regulations, validate.